The PRINCE2 Process, Managing Product Delivery (MP) sets down the basic steps for a Team Manager to manage the interface between and external team and the Project Manager.

What is it? MP is a smaller version of Controlling a Stage. This is because the Team Manager accepts the Work Packages after agreeing them with the Project Manager, actually executes the packages and delivers them back to the Project Manager.

The aims of the process centre on individual packages. For each Work Package-


 *Negotiate details of the Work Package with the Project Manager
 *Plan, allocate, track progress, report progress, record in the Quality Log, control changes all within the package.
 *Give it back.

An essential element of the process is "agreement". The Project Manager does not just dish out Work Packages and expect them to be done. The Team Manager has to "accept" it with its various constraints and requirements. Conversely the Project Manager should have a reasonable expectation that sufficient resources will be provided, and their level agreed beforehand.

Why? Although the Project Manager has day-to-day control of the project, the work to produce something tangible still has to be done.

MP creates a mechanism through which the Project Manager can ensure that work is actually carried out. From the Team Manager's perspective, she can allocate resources and complete work to deadlines with more purpose.

The Team Manager has a mechanism for fulfilling her role of ensuring production of products defined by the Project Manager to an appropriate quality, in a timescale and at a cost acceptable to the Project Board.

Who The main player in MP is the Team Manager who has responsibiltity for production of the products.

The Project Manager is a party by virtue of the fact s/he has to agree the Work Package.

There may be more than Team Manager. For instance their may be a network manager, who accepts a Work Package based on ensuring bandwidth and test team manager, who has to ensure software meets requirements.

How There are 3 sub-processes in MP:-


 *Accepting a Work Package (MP1)
 *Executing a Work Package (MP2)
 *Delivering a Work Package (MP3)

There are a number of products which may be created or updated-


 *Agreed Work Package Team Plan
 *Updated Risk Log
 *Checkpoint Reports
 *Updated Quality Log
 *Updated Issue Log
 *Updated Team Plan
 *Approved Products
 *Completed Work Package

Related Articles
PM
MP
Java - process
Managing Stage Boundaries
Closing A Project
Controlling A Stage CS
Xansa and Tesco Outsourcing
ITIL - programme

Similar Areas

Process Improvement Items

Project Management Items

UK Government Items

Management Items

Public Sector Items

Selected Books

Keywords

Managing Product Delivery

MP

PRINCE2

PRINCE 2

PRINCE2 process

process

PRINCE2 sub-process

Project Manager

PM

project management

Team Manager

work packages

Quality Log

Work Package Team Plan

Risk Log

Checkpoint Reports

Issue Log

Team Plan

Approved Products

Completed Work Package


See our Sarbanes-Oxley compliance, load testing and Financial Glossary pages.
Articles   Books   FAQ Page   home   Jobs   Links   Reviews Page   Tools  
Booklist   books   Measurement   Testing   Tools